Waitsfield water project update 11-10-2010

{mosimage}

 

Contract #1: J. P. Sicard will be continuing with the water installation on Route 100 heading north from Village Green and ending just south of Full Circle Auto by the end of November. VTrans requires that all work in the Route 100 ROW must be suspended as of December 1.

Sicard will move to Dugway Road around the first of December and take about two weeks to complete that work. Lane closures will continue on Route 100. Drivers are advised to use caution and to pay attention to the flaggers.


Contract #2: Munson Earth Moving should complete permanent pavement repairs on Tremblay Road this week, weather permitting. Directional bore #3 on Tremblay Road under the Mad River should be completed this week and Bore #1 will follow starting north of Kenyon's Store and ending near Amerigas.

Contract #4: Kingsbury Companies is continuing water main installation along East Road to the exit point of Bore #2 and then jump to Long Road and continue to Reed Road. Directional Bore #1 from Bushnell Road to the Dump Road will be completed this week. Bore #2 which runs under the crest of East Road to the intersection of Long Road will start within the next two to three weeks.